Do not look now more wait for when? ! Construction of ministry high speed has significant progress a

11 small long holidays just passed

Freeway of Su Xichang south does not have stannic mark paragraph

Have new information again

Today midday

Too in lake channel lake dark bury paragraph

First motherboard is irrigated formally build

Indicating

Do not look now more wait for when? ! Construction of ministry high speed has significant progress again south Su Xichang! Bring your sound one explore too of lake channel " bottom " !

Construction of tunnel of bottom of lake of high speed of Su Xichang south is built

Already entered phase of project of underwater channel main body

Do not look now more wait for when? ! Construction of ministry high speed has significant progress again south Su Xichang! Bring your sound one explore too of lake channel " bottom " !

Small make up this to bring your sound one explore too of lake channel " bottom "

Po spot is illuminated came

↓ ↓ ↓

Do not look now more wait for when? ! Construction of ministry high speed has significant progress again south Su Xichang! Bring your sound one explore too of lake channel " bottom " ! Do not look now more wait for when? ! Construction of ministry high speed has significant progress again south Su Xichang! Bring your sound one explore too of lake channel " bottom " ! Do not look now more wait for when? ! Construction of ministry high speed has significant progress again south Su Xichang! Bring your sound one explore too of lake channel " bottom " !

In irrigating built lake today dark bury paragraph

First channel motherboard

20 meters long, 43.6 meters wide, thick 1.4 meters

Irrigate build an area 868 square metre

Do not look now more wait for when? ! Construction of ministry high speed has significant progress again south Su Xichang! Bring your sound one explore too of lake channel " bottom " ! Do not look now more wait for when? ! Construction of ministry high speed has significant progress again south Su Xichang! Bring your sound one explore too of lake channel " bottom " !

After building as a result of channel

Motherboard wants to be in for a long time

Underwater the position end 11 meters lake

Accordingly

Waterproof job

The Chongzhongzhi that also made construction is heavy

Do not look now more wait for when? ! Construction of ministry high speed has significant progress again south Su Xichang! Bring your sound one explore too of lake channel " bottom " ! Do not look now more wait for when? ! Construction of ministry high speed has significant progress again south Su Xichang! Bring your sound one explore too of lake channel " bottom " !

In Di Peng of chief engineer of project of tunnel of bottom of 4 bureaus lake introduces iron

Belt of type shut-off of water is stuck outside having outside motherboard

Belt of shut-off of water of edge having steel is buried in

Contain inside but belt of discharge type shut-off of water

Need not worry so

Long park benthic

Predict first motherboard is irrigated build finish

Will need 15 hours

Irrigate in all build concrete 1278 stere

Di Peng tells a reporter

Irrigate build after finishing

They should undertake maintaining

The construction that has side wall and roof next is irrigated build

Do not look now more wait for when? ! Construction of ministry high speed has significant progress again south Su Xichang! Bring your sound one explore too of lake channel " bottom " !

End at present

Channel of bottom of lake of high speed of Su Xichang south

Na Quan paragraph 4 construction cofferdam already finished pump water to work

Among them, the first with the 2nd storehouse cofferdam

Undertaking excavate of cubic meter of earth and construction of main body structure

Cofferdam is in the 3rd storehouse undertake fighting unplugging picket construction

Cofferdam is in the 4th storehouse clear silt

Cheng of bank go to work already finished n at present paragraph 140 meters of motherboard are irrigated build

Predict by this year

The main body project of channel of bottom of this part lake

Will irrigate build finish

At the appointed time too the main body structure of lake channel

Also will show went out

Do not look now more wait for when? ! Construction of ministry high speed has significant progress again south Su Xichang! Bring your sound one explore too of lake channel " bottom " !

Before this, predict too project of lake channel main body

Will in December 2020 complete

Will become at the appointed time

Home is the longest the widest underwater channel

And freeway of Su Xichang south

Predict 2021 the copy is complete

Do not look now more wait for when? ! Construction of ministry high speed has significant progress again south Su Xichang! Bring your sound one explore too of lake channel " bottom " !

After be open to traffic

Do not have the change a travel of stannic person

With respect to spirit of go off with hill is exemple

Set out from citizen center now

Go going to clever Shandafo

If take ring too lake highway

Add up to 38 kilometers, need 55 minutes.

After waiting for be open to traffic of high speed of Su Xichang south

Require run of about 25 kilometers only

Predict less than can be arrived at half hours!

Save half the time!

If from Na Quanshu button sets out

Pass through directly channel arrives Ma Shan

Want the most quickly only 10 come minute!

Ask you period wait for!

Do not look now more wait for when? ! Construction of ministry high speed has significant progress again south Su Xichang! Bring your sound one explore too of lake channel " bottom " !

Reporter: Yan Yongqing, Wang Jing